Description
The TPS is a newly constructed 3-GeV third-generation synchrotron light source featuring ultra-high photon brightness with extremely low emittance. After some hardware improvement especially demagnetization of chamber are completed, the commissioning of the beam in the booster ring began on December 12 and attained 3-GeV energy on December 16. The storage ring obtained its first stored beam and delivered synchrotron light on December 31. This report summarizes the role of beam diagnostic for hardware improvement and parameter tuning during TPS successful commissioning.